English Partnerships this month launched a strategy to develop the UK's brownfield sites. Atkins head of regeneration and economic development, Steven Cox, takes a look at the report and asks: is this a new hope for brownfield regeneration?

BRITAIN’S LEGACY of previously developed land (PDL) has arisen due to changing economic factors and Government policies in the post-war period. As the country’s traditional industrial and economic base eroded in the face of global competition, many of our factories and manufacturing plants closed from the 1960s onwards. The process of economic restructuring from a manufacturing-based to a service sector-based economy is still underway in many parts of the country, especially the northern and peripheral regions.Image

Simultaneously, from the 1950s onwards the Government embarked on a policy of population dispersal, which led to new towns, expanded towns and peripheral housing estates being built around the country. These dual forces have resulted in greater demand for greenfield, undeveloped land for housing, while the supply of brownfield, PDL, has increased.

Dealing with the brownfield legacy Since the 1970s, there has been a concerted effort by politicians, policy makers and regeneration practitioners to ensure PDL is reused wherever practicable, through interventions such as Urban Development Companies, Enterprise Zones, City Challenge, Urban Regeneration Companies and many others. However, the results have been mixed.

The level of success can be attributed to several factors; the skill and knowledge of those dealing with PDL in an area; the amount of dedicated funding available to tackle the issues; the range of barriers evident on a site and the fundamental issue of market demand and development economics.Image

In order to give renewed impetus to the brownfield regeneration process, English Partnerships (EP) has, over the last few years, worked on the production of a National Brownfield Strategy.

Brownfield Guide: a practitioners guide to land reuse in England was launched earlier this month. EP will make recommendations to the government to follow this report in February 2007.

The scale of the brownfield legacy is massive. According to the latest estimates from EP, there were 64,000 hectares of PDL in 2004; a reduction from 66,000 in 2002. Clearly, many of these sites are not in a state which allows them to be brought back into productive use easily and it is these more difficult sites which the Brownfield Guide is designed to focus upon.

A team of specialist regeneration consultants from Atkins and Lambert Smith Hampton has supported the development of the Strategy by conducting strategic, evidence gathering pieces of research work on the Barriers to Regeneration. The companies focused on a sample of 140 sites in 14 Local Authority areas across England.

In the study, Economic Benefits of Recycling Brownfield Land, they looked at the positive outcomes that could be achieved on around 300 sites in 30 Local Authority areas.

Land problems

The study found problems associated with contamination and development can deter development on a site, and act as a significant barrier. The length of time involved in site monitoring, remediation and decommissioning can deter developers and these sites tend to remain undeveloped unless the public sector can remove development barriers or the market improves to such a degree that the return on investment exceeds the cost of site remediation and preparation. In Northern and peripheral regions the prospect of contaminated sites being reused is less than in the South-East.

Land Ownership Barriers make it difficult to develop brownfield sites. Assembling the various title interests in land can be time consuming and expensive. Problems can also be encountered in terms of identifying owners, leases and licences, ransom strips, multiple ownerships, unrealistic sale value expectations of the owners and owners who refuse to sell.

The study found developers will look for less complicated sites, instead of using sites where they see the ownership and assembly barriers are too great. Compulsory Purchase Orders (CPOs) can help but they too can be problematic, expensive and are therefore often seen as a last resort.

Site accessibility is also important in terms of the ability for people to get to work, for customers to get to a location and for goods to be delivered. Public transport access is also important for residents to go about their daily business too. Poor infrastructure can also deter planning permission being granted if the scale of development can not be adequately serviced.

Ecological barriers

Over time, there is potential for vacant sites to become colonised by plants and animals attracted to the undisturbed nature of the site or its particular soil conditions. These sites may then be given different forms of protected status, which slows down the development process and can even render sites unsuitable for development.Image

Heritage sites, which include listed buildings, World Heritage Sites, Ancient Monuments, Battlefields, historic parks and gardens, do not preclude development, but they do often require special consents and are material considerations in the planning process.

However, heightened costs are not the sole barrier to develop heritage sites; they often contribute to a local feeling of place and community and act as landmarks, and local residents can often be opposed to them being redeveloped or changed in any way.

Funding barriers

A significant volume of PDL sites sit within areas of market failure and low demand where the costs of site preparation and construction are greater than the returns that may be achieved. Public sector grant aid is often available to assist in this process, but it is perceived as being bureaucratic, difficult and a further barrier to regeneration.

Developers now generally work to a profit on cost of something like 20%. If end sales values are high enough to cover this profit margin, then developers will be prepared to consider paying out for remediation, land assembly, environmental considerations and good design.

However, if the end sales values do not cover this profit margin then developers will simply look elsewhere. The fundamental issue of development economics and site profitability are the core barrier to regeneration. This is particularly an issue in areas of market failure and low demand.

Socio-economic barriers

Within the planning, regeneration and development professions there is a skills gap in terms of the ability to deal with issues of CPOs, remediation and large-scale external funding bids. The existence of this barrier is linked to a lack of vision and aspiration in some areas, which is more difficult to address. Other socio-economic barriers are difficult to quantify but they do have an impact on market demand and profile of an area. The better the socio-economic base the more desirable an area will be for developers and vice versa. Skills deficits in an area can also counter against inward investment and development projects taking place.

Derelict or PDL is often thought of as a legacy of the Industrial Revolution and associated industrial processes. This is only part of the picture. While a portion of the stock of PDL has been lying vacant and derelict since the nation industrialised, the overall total stock of PDL has been added to over time and is continuing to be added to.

Even if success is achieved in reusing more of the stock of PDL, the process which leads to land falling out of productive use in the future will continue due to structural changes in the economy, locational preferences of business and investors, technological advances, socioeconomic change and policy instruments. The difference in the future will be that the Brownfield Guide will provide advice and guidance to practitioners as they grapple with the complex issues around brownfield redevelopment and regeneration.


 

The Directory

Events

Interbuild

26th-30th October 2008 - NEC, Birmingham

 

National Engineering & Construction Recruitment Exhibition

15th-15th November, 2008 - Olympia, London

 

Civils 2008

18th-20th November, London Earls Court 2

 

Ecobuild/Futurebuild

3-5th March 2009 - Earl's Court, London

 

National Homebuilding and Renovating Show 2009

19-22nd March 2009 - NEC, Birmingham  

 

SED 2009

12th-14th May, 2009 - Rockingham Motor Speedway, Corby

 

Sustainabilitylive!

19th-21st May 2009 - NEC, Birmingham