| Crossrail under the spotlight |
|
| Thursday, 18 September 2008 | |
|
Crossrail MD Keith Berryman on contractors, contingencies, and crossing under London TWO DAYS after the Crossrail Bill achieved Royal Assent, its managing director Keith Berryman, who since August 2000 has been steering the Bill through Parliament, is showering his staff with gifts. “I’m sorry I’m late,” he says, out of breath, “I had to pop to the house to get some presents for people who are leaving.” Now the Crossrail Bill has been passed, Keith Berryman’s parliamentary team is moving on. For more than eight years he has led a team of 75 people within Cross London Rail Link (CLRL) in getting the Crossrail Bill through Parliament. After a torturous 20-year journey, the £16bn project to link Heathrow directly with London’s financial district has got the green light. But for Berryman, 61, there is still much work to be done. By the time he’ll be able to ride the length of Crossrail – from Sheinfield in the east to Maidenhead in the west – he’ll be five years into retirement. “I was actually on holiday when Gordon Brown came round to the office to tell us we had got the funding,” he says. “My assistant rang me in Marbella to tell me.” Crossrail’s 40m-deep tunnels will pass beneath the capital’s streets, passing by and below existing underground lines. It will mean existing underground stations will need to be extended below ground to service the new route. As a result, there will be new stations at Paddington, Bond Street, Tottenham Court Road, Farringdon, Whitechapel, Liverpool Street and the Isle of Dogs. Fresh from the scrutiny of Parliament, Berryman finds time to put the scope of Europe’s largest civil engineering project into perspective. What is the value of Compulsory Purchase Orders needed for Crossrail? Do you envisage problems with the CPOs? What amendments were made to the Bill in Parliament? Will the new station at Woolwich add to the cost? You’ve said construction ought to follow the strategy of Terminal 5. What did you mean? How will you be sharing the risk? We have one delivery partner who helps us with the programme management – that’s including what Network Rail does and what other members of the scheme do. Then we have another delivery partner – likely to be a separate one – who will be responsible for the new works which we’re building on our own and we’ll be heavily influenced by their approach. What did you learn from the contractual horrors of the Channel Tunnel? How many main packages will there be for contractors? Will you be using project bank accounts? Has the central tunnel route been compromised since it was first proposed in the 1990s? The scheme we’ve got now is a bit different but the Liverpool Street to Paddington section has substantially used the alignment that was safeguarded. There have been some developments, mainly buildings with piled foundations, which have led to minor adjustments. What are the biggest excavation challenges? In the eastern part of London, particularly where the Pudding Mill portal is, there are a number of interesting challenges where we go directly underneath the River Lea. There are also National Grid’s 400 kV underground cables that are in the towpath of the River Lea, and that’s going to cause quite a problem. The ground is not too bad. It’s the proximity of the At Whitechapel we’ve got some piled foundations that we’ll have to modify. We’ve also got bad ground in the Farringdon area that’s receiving a lot of attention. How will you deal with the intricacies of integrating new stations with existing one’s? There is a lot of negotiation with Network Rail and London Underground about how we interface with their works. Like any bureaucracy there are always challenges. Generally speaking, those relationships are pretty solid. Where we break into the London Underground stations is complicated. There are a lot of issues around standards and procedures because running a railway service underground is something that requires high regard for safety. If it isn’t done properly it is dangerous. For that reason you have a lot of procedures, systems and methods of working designed to ensure safe conditions, but they aren’t always conducive to doing works on the stations for obvious reasons. What risks have you recognised and what contingencies do you have? We’ve been heavily involved in setting up an academy for tunnellers and other kinds of training schemes in conjunction with the industry. In the case of tunnelling we will probably be taking the lead on that. Did you fear the project would be put-off again in the current economic climate? But won’t it absorb labour? Will contractors only be allowed to use directly employed labour? When will the first heavy construction work begin? The first construction work will be Tottenham Court Road Station, which we’ll be doing jointly with London Underground. They have a serious problem at Tottenham Court Road with congestion and they’re anxious to get on with it as quickly as possible. The next one will be the Isle of Dogs Station at Canary Wharf, which will probably start early next year. Boris Johnson has warned that Crossrail must not take priority over the upgrade of London’s tube network. Is he right to be concerned?
|


